Game Changer: DEQ Takes A Fresh Look At Shutting Down Boardman

June 28, 2010
By

PGE's coal fired Boardman Power Plant. Photo from Ted Timmons

The news must have landed at PGE like a ton of coal.

Oregon DEQ says its looking at three options for an early closure of PGE’s coal-fired power plant at Boardman. They call on the utility to spend millions more to keep the plant running, or shutting it down a lot earlier than PGE wants.

The Big Picture

To see where this is going, let’s back up for a moment. There’s only one approved plan – so far – that allows PGE to continue operating the Boardman power plant. It allows the plant to generate electricity by burning coal until 2040. But PGE would have to install about $500 million in new pollution controls to bring down emissions of nitrogen oxide, sulfur dioxide.

This doesn’t include any controls on greenhouse gases. None are required for now, but pretty much everyone expects they will be required in the near future. Since Boardman is the state’s biggest single source of greenhouse gas, the costs of new controls could be substantial.

PGE, no surprise, would like to avoid having to pay for all that. So earlier this year it proposed a plan where it would shut down Boardman by 2020, and only have to spend about $40 million on pollution controls. That proposal was rejected by DEQ a couple of weeks ago.

DEQ’s Options

The 2020 Plan: Boardman shuts down by the end of 2020, and PGE spends $320 million on reducing pollution.

The 2018 Plan: The plant closes by the end of 2018, and PGE pays about $100 million for new controls.

The 2015-2016 Plan: Boardman shuts down in late 2015 or early 2016. The cost of pollution controls drops to $35 million

DEQ says it chose these options because it thinks they can be approved by the EPA. It’s now taking comments from the public, plans on holding hearings in September, with a goal of approving a final plan before the end of the year.

Environmental Reaction

Oregon Sierra Club, which has been leading the campaign to shut down Boardman, is praising DEQ for the new proposals. The group wants Boardman closed in 2014. While DEQ doesn’t go that far, it does get us closer.

In a statement, Cesia Kearns of the Coal Free Oregon Campaign writes:

“The options DEQ has proposed demonstrate clearly that PGE can and should phase-out their dirty and dangerous Boardman coal-fired power plant earlier than the 2020 they are currently proposing. We already know that it is better for public health and the environment in Oregon if Boardman is phased out soon. The options offered by DEQ today further detail how it will also be cheaper to phase the plant out sooner than PGE is currently considering.”

PGE Reaction

The utility is not happy with the DEQ options. It wants to keep Boardman running until 2020, but at a lower cost. It says it needs the extra time to plan and develop cleaner sources of electricity to replace the plant.

According to PGE President and CEO Jim Piro:

“We put forward a plan for Boardman that we believe reached a good balance between cost, risk and environmental benefits. We’ll do a complete analysis, but we’re disappointed that DEQ didn’t allow that plan to proceed. On the face of it we believe the new options DEQ put forward today may reflect an extreme interpretation of federal rules that won’t make sense for our customers or our state. We want to work with DEQ to find a better way to transition this resource around the 2020 timeframe.”

The Next Steps:

DEQ sets up an advisory committee to do further study, which starts meeting in July. An updated version of this plan would be ready for public hearings in September. But the agency is taking comments now and they can be emailed to, deqoptionspge@deq.state.or.us.

For More Information:

Draft DEQ Proposal for Early Shutdown of the PGE Boardman Plant

PGE Reaction

Sierra Club Reaction

Share

Tags: , , , , ,

One Response to Game Changer: DEQ Takes A Fresh Look At Shutting Down Boardman

  1. [...] This post was mentioned on Twitter by Natural Oregon, PDXLeftSide. PDXLeftSide said: Natural Oregon: Game Changer: DEQ Takes A Fresh Look At Shutting Down Boardman: The news must have landed at P… http://bit.ly/dmSGuB #pdx [...]

Leave a Reply

Your email address will not be published. Required fields are marked *

*